Mining group Armadale Capital said the estimated cost of developing its Mahenge Liandu graphite project in south-east Tanzania had risen to $39.7m, though so had its output potential and overall value.

The numbers were given in an updated definitive feasibility study, the previous of which had pegged project capex at $38.6m.

The project's estimated life had been shortened to 15 years, from 17 years, but its average annual graphite production upped 30% to 109k tonnes per annum.

Its re-tax net present value was increased 20% to $430m with an internal rate of return of 91%.

The $39.7m capital cost estimate included contingency of U$S4.1m or 15% of total direct capital cost.

First production was expected to occur about 10-12 months from the start of construction.

Chairman Nick Johansen said the updated study lent support to ongoing discussions for binding offtake agreements, debt package finance for construction and project-level development funding.