W Resources says La Parrilla commissioning on track for July

Writer,

Archived article

Please note that tax, investment, pension and ISA rules can change and the information and any views contained in this article may now be inaccurate.

W Resources said the commissioning of a concentrator at its La Parrilla mine in Spain was on track for completion in July.

Primary equipment installation and construction was complete for the spirals and shaking table buildings of the concentrator.

A small FME building was on track for primary construction completion next week, following installation of a filter press.

Commissioning of a jig and mill was also proceeding well, the company said.

'W Resources completed the Blackrock debt financing in May 2018 and it is a great credit to our team and suppliers that some 14 months later we are on the cusp of construction completion and have commissioned the crusher, jig, LNG power plant and other major non plant equipment,' chairman Michael Masterman said.

At 8:02am: (LON:WRES) W Resources PLC share price was 0p at 0.44p